04/14/2014

The City of Mesa has selected Blucor Contracting for the Broadway Road Improvements project.

Concrete work continues on the north side of Broadway Road including driveways, ramps and catch basins. Water line tie-ins will begin this week starting at Sossaman and work their way east. Subgrade has passed on Broadway Road from Sossaman to 80th Street and AC millings are being spread and compacted. Landscape irrigation continues on the south side of Broadway Road.

Project Schedule

Construction began the week of September 3, 2013 and is expected to be completed in July 2014.

Project Details

Proposed Broadway Road improvements include two through lanes and bike lanes in each direction, a striped median and new curb, gutter and sidewalk.

The existing inverted crown in Broadway Road from Sossaman to Hawes Roads, which allows storm water to pool and flow down the center of the street, will be removed and replaced with a City standard crowned roadway section. The new City standard crowned roadway will help address drainage issues by sending water to the storm drain system along the curb and gutter and the newly installed catch basins. The Sossaman and Broadway Road intersection will include dual left turn lanes in all four directions.

Project Funding

The project is funded by voter approved transportation bonds from the November 2008 City Bond Election.

 

 

 

Project Location Map

Fact Sheet

Landscape Plan

Construction Progress Photos

Road Closures and Lane Restrictions

Engineering Home

Find us: mctraffic  Facebook Icon  Twitter Icon

Open during Construction

 

The businesses listed below are participating in our Shop Mesa program and are offering some great construction specials! Be sure to check them out!