Brooks and Lindsay Pump Station Improvements

Project Number 01-606-002


 

Project Updates

02/25/2013

 

The City of Mesa has awarded this project to the MGC Contractors Inc.

TThis project is complete

Project Schedule

Construction on this project began in late September 2011 and is estimated to be completed in April 2013.

Project Details

The Brooks Pump Station was built in 1974 and includes a pump station, with eight existing pumps, a 10 million gallon reservoir and a well site.  Several existing pumps and motors are past their useful life.&

The Lindsay Pump Station was built in 1978 and includes a pump station with eight existing pumps, and a 10 million gallon reservoir.  Like the Brooks Pump Station, several of the pumps and motors are past their useful life.  The pump station experiences operational problems with the pumps, failures of pump impellers, a problematic reservoir mixing system, and other issues that continue to affect the pump station life and performance.

This project will increase station pumping capacity to meet existing water demands in the City Water Zone as well as the projected water demands anticipated in the current Water Master Plan.  This project will also improve water quality, improve the operation of the pumps, install premium-efficiency motors, and install safe and reliable chlorination systems.


Project Funding

The recommended total award amount for this project is $6,963,907.50, based on the low bid of $6,330,825.00 plus an additional $633,082.50 (10% allowance for change orders).  This project is funded from the FY 10/11 Water Bond Capital Program.