Brown Road Water Treatment Plant Security Wall

Project Number 10-602-002


 

Project Updates

05/13/2013

The City of Mesa has awarded this project to R.K. Sanders, Inc. 

The contractor work is complete.

Project Schedule

Construction on this project is scheduled to begin at the end of August 2012 and is estimated to be completed in May 2013.

Project Details

The Brown Road Water Treatment Plant (BRWTP) located at 7750 E. Brown Road was originally constructed in 1985.  The plant currently treats water from the Central Arizona Project Canal, and then transfers treated water to the distribution system.

The goal of this project is to provide a higher level of security applicable and consistent with current regulatory guidance and industry standards.  The project will also replace the front entry gate and a motor that is undersized and has a history of requiring frequent maintenance.


Project Funding

The recommended total award of this project is $1,118,596.89, which consists of the lowest bid of $1,016,906.26 plus an additional $101,690.63 (10% allowance for change orders).  Funding is available from the FY 11/12 Water Bond Program.