Crismon Road Improvements South of Skyline High School and Signal Butte Road Capacity Improvements at US HWY 60

Project Number 10-455-001


 

Project Updates

08/20/2012

 

The City of Mesa has awarded this project to Visus Engineering Construction, Inc.

The project is complete just waiting for the City of Mesa to stripe the roadway.

 





Project Schedule

 

Construction on this project is scheduled to begin in August 2012 and be completed by October 2012.

Project Details

 

This project will widen the west side of Crismon Road to ultimate width by constructing new curb, gutter, and sidewalk.  The existing traffic signal at the south entrance to Skyline High School will also be relocated to accommodate the widening of the street.  The City of Mesa has purchased right-of-way from the property owner on the west side of Crismon Road to facilitate this project and is placing a scalloped lien against the undeveloped parcel on the west side of the road for the proposed street improvements, as previously approved by City Council.

The property on the east side of Crismon Road is currently under development and the required Crismon Road street improvements will be completed by the developer at a future date, when the development reaches that phase.  As an interim improvement, this project will improve pedestrian safety by widening the pavement on the east side of the roadway to create a 6’ wide temporary paved walkway for pedestrians.   This project will also construct temporary curbing to separate the vehicle lanes from the pedestrian route to better enhance safety.  When the developer on the east side of Crismon Road completes his improvements to Crismon Road, the paved pedestrian path will become part of the improved roadway (replaced by permanent sidewalk) and the temporary curbing will be removed.

The proposed improvements at Signal Butte Road and U.S. Highway 60 will widen the existing northbound left turn lane to include dual left turn lanes for traffic going west, onto the freeway.  The existing raised concrete median will be demolished and re-installed as flush concrete to provide the second left turn lane.  These improvements will provide additional capacity for the heavy left turn movement and allow the left turn signal to be changed to “fully protected”.  This will improve traffic safety by not allowing drivers to make left turns while oncoming traffic also has a green signal. 

 

Project Funding

 

The recommended total award of this project is $145,596, which consists of the low bid of $132,360, plus an additional $13,236 (10% allowance for change orders).  This project is funded from the FY 11/12 Streets Bond and Streets Capital Programs.