The City of Mesa has awarded a Job Order Contract to B&F Contracting. Construction began on 8th Street and Harris Drive and will move north on Harris Drive towards Brown Road.

The new water line has been installed 30 feet south of Brown Road. The contractor is working on water line tie-ins throughout the project. Trenching, milling, and adjustments will commence after completion of the tie-ins and abandonments.

Project Schedule

Construction started March 17, 2014 and will be completed late August 2014.

Project Details

Project will include replacement of a waterline on Harris Drive between 8th Street and Brown Road. The work will include the connection of a new 12-inch waterline to accommodate future use without the worry of breaks in the existing line.


Project Funding

This project is funded by the voter approved 2010 Water Bond Fund.

 

 

Road Closures and Lane Restrictions

Engineering Home

Find us: mctraffic  Facebook Icon  Twitter Icon

Open during Construction

 

The businesses listed below are participating in our Shop Mesa program and are offering some great construction specials! Be sure to check them out!