Mariposa Park: Medina and Hawes Park and Roadway
Project Number CP0009


 

 

Project Updates

11/03/2014

 

This project has been awarded to Valley Rain one of our Job Order Contractors for the improvements to the park and Talis Construction for the improvements to the roadway.

Valley Rain has completed the majority of the site grading and concrete walkways are being constructed. They have started storm drain work and installing irrigation lines as well. Installation of playground equipment will take place mid December.

Talis Construction has begun to grade the roadway and SRP power lines are being undergrounded. Waterline installation has begun

Project Schedule

Construction began July, 2014 and will completed early February 2014.

Project Details

The City of Mesa intends to construct a new park on the northeast corner of Hawes Road and Medina Avenue and complete the roadway improvements to the adjacent streets. In addition, the City's well site on the northwest and southwest corners of the park site will be reconfigured.


Project Funding

The funding for this project comes from Water Resources, Transportation and 2012 Park Bonds.

 

Parks and Recreation 2012 Bond Program

Conceptual Rendering

Conceptual Amenities Rendering

2013 Public Safety and Street Bonds

Engineering Home

Contact us: Facebook Icon  Twitter Icon

http://www.mesaaz.gov/engineering/Images/YPTP.png

 

The Mesa Parks, Recreation and Commercial Facilities Department is committed to providing sustainable facilities and opportunities to enhance the quality of life and well being of our community. 

 

Parkyourquestions