 7/28/14 

The City of Mesa selected Garney Construction as the Construction Manager at Risk (CMAR) for this project.  During construction, your contact for Garney Construction is Shane O'Brien at (480) 213-8859. 

Crews continue to excavate and install the 72-inch water line in Lindsay between McKellips Road and Brown Road.  Pulverizing (removing asphalt) the trench line from the SRP canal to Brown Road is complete.  Crews are have approximately 300 feet of pipe left to install between Hope Street and Brown Road.  Beginning Thursday, July 17, crews will begin (24-hour operations) pipe installation on the southern half of the intersection with a support crew laying 60-inch pipe on Brown Road, west of Lindsay Road.  Paving the southern half of the Brown Road and Lindsay Road intersection is tentatively scheduled to take place the week of August 4, 2014.              

Traffic Restrictions:

Traffic is currently switched to the east side of Lindsay Road from just south of McKellips Road to Brown Road with one lane in each direction.  Left turns will be prohibited at the intersection of Brown Road and Lindsay Road from July 17, 2014, through early September 2014.  There is one right turn prohibition for eastbound to southbound traffic.

Project Schedule

Construction began January 13, 2014, and will last approximately one year. 

Project Details

The City of Mesa plans to construct improvements to its water transmission system to modify the method of delivering water from the Val Vista Water Treatment Plant.  The first phase of this project includes installation of a new 72-inch water transmission main along Lindsay Road from the Val Vista Water Treatment Plant at McDowell Road to Brown Road.  Also included is the installation of a new 60-inch water transmission main along Brown Road from Lindsay Road to 24th Street.

Project Funding

The recommended total award for the GMP No. 1 is $3,315,878.41 based on the material cost of $3,157,979.44 plus an additional $157,898.97 (5% contingency allowance for change orders).  This project is funded by the voter approved 2010 Water Bond Fund.

 

 

 

 

Tentative Construction Phasing Plan 

Alternate Bike Route During Construction

Road Closures and Lane Restrictions

Business Promotional Page

Engineering Home

Find us: mctraffic  Facebook Icon  Twitter Icon

 

Open during Construction

The businesses listed below are participating in our Shop Mesa program and are offering some great construction specials! Be sure to check them out!