Paths - $12.4 M
Lehi Crossing Shared Use Path
Construct a 2.2 mile path from McDowell Road to Loop 202 near Lehi Crossing.
Contact: Curt Albright, City of Mesa 480-644-3800 or Engineering.Info@MesaAZ.gov
Project Timeline:
- Design -Complete
- Construction -TBD
Eastern Canal Shared Use Path
Improve 2.3 miles along the Eastern Canal with a focus on signalized pedestrian crossings from Brown Road to Broadway Road.
Project Timeline:
- Design - Summer 2022
- Construction - Fall 2023